The purpose of this single-sheet reference is to: Define common Earned Value Management (EVM) terminology ''alphabet soup''. List EVM metric equations. Labels the most common EVM graph. It also summarizes DoD EVM policy.
This DOE EVMS Gold Card is a single-sheet reference that defines common Earned Value (EV) terminology (''alphabet soup'').
evm policy In accordance with DODI 5000.85 Major Capability Acquisition, EVM is required for cost or incentive contracts, subcontracts, intra-governmental work agreements & other agreements (except for those that are primarily software) valued at $20M or more.
Additional Guidance in Defense Acquisition Guidebook & Earned Value Management Implementation Guide (EVMIG) EVMS is discouraged on Firm-Fixed Price & Time & Material Contracts; & LOE activities regardless of cost.
Earned Value Management System (EVMS) Gold Card. This DOE EVMS Gold Card is a single-sheet reference that defines common Earned Value (EV) terminology (''alphabet soup''), lists EV metric equations, and labels the most common EV graph.
The EVM Gold Card defines common EVM terminology, lists EVM metric equations, lables the most common EVM graph, while summarizing DoD EVM policy. Acquisition Regulation Comparator (ARC)
The National Defense Industrial Association (NDIA) / Electronic Industries Alliance (EIA) standard EIA-748, Earned Value Management Systems (EVMS), is the standard for DoD Earned Value Management programs.
Earned Value Management (EVM) is a widely accepted industry best practice for program management that is used across the Department of Defense (DoD), the Federal government, and the commercial sector.
DOE EVMS GOLD CARD. PERFORMANCE BASELINE COMPONENTS (Performance Baseline must clearly document scope/KPPs, TPC and CD-4 date) AUW= Authorized Unpriced Work (contractually approved, but not yet negotiated) CA = Control Account (includes AUW) = WPs + PPs . CBB = Contract Budget Base = PMB + MR . CP = Contract Price = CBB + profit/fee
In accordance with DODI 5000.85 Major Capability Acquisition, EVM is required for cost or incentive contracts, subcontracts, intra-governmental work agreements & other agreements (except for those that are primarily software) valued at $20M or more.